DHB Meegahakiula

Status  :  Completed

Date of Commencement  : 12th August 2019

Date of Completion  : 06th November 2020

Contract Value  :  Rs 22.89 Million

Contractor  :  Wijewardena Construction

Previous Next

DHC Haldummulla

Status  :  Completed

Date of Commencement  :  06th January 2020

Date of Completion  :  15th March 2021

Contract Value  :  Rs 32.64 Million

Contractor  :  Senarathna Construction

Previous Next

DHB Koslanda

Status  :  Completed

Date of Commencement  :  06th January 2020

Date of Completion : 06th March 2021

Contract Value  :  Rs 27.16 Million

Contractor  :  Chathura Construction

Previous Next

DHB Kandeketiya

Status  :  Completed

Date of Commencement  :  06th January 2020

Date of Completion  :  29th March 2021

Contract Value  :  Rs 30.06 Million

Contractor  :  Kondesingha Construction

Previous Next

DHC Ettampitiya

Status  :  Completed

Date of Commencement  :  11th January 2020

Date of Completion  :  28th June 2021

Contract Value  :  Rs 40.01 Million

Contractor  :  Kondesingha Construction