Civil Works Round 1

Previous Next

DHC Endana

Status  :  Completed

Date of Commencement  :  21th August 2019

Date of Completion  :  20th August 2020

Contract Value  :  Rs 18.72 Million

Contractor  :  KEP Construction 

Previous Next

PMCU Dodampe

Status  :  Completed

Date of Commencement  :  21th August 2019

Date of Completion  :   20th August 2020

Contract Value  :  Rs 27.50 Million

Contractor  :  Mohan Enterprises

Previous Next

DHC Ranwala

Status  :  Ongoing

Date of Commencement  :  10th March 2020

Expected Date of Completion : 09th March 2021

Contract Value  :  Rs 21.04 Million

Contractor  :  Arcyn Engineering

Previous Next

PMCU Narissa

Status  :  Ongoing

Date of Commencement  :  10th March 2020

Expected Date of Completion : 09th March 2021

Contract Value  :  Rs 31.78 Million

Contractor  :  KEP Construction

Previous Next

PMCU Delwala

Status  :  Ongoing

Date of Commencement  :  10th March 2020

Expected Date of Completion  :  09th May 2021

Contract Value  :  Rs 19.66 Million

Contractor  :  Arcyn Enginnering